The short version

The CAPA owner says the tooling change is complete. The process failure mode and effects analysis (PFMEA) says the new control is installed. The risk register says both machining cells are protected. A walk to cell B finds the old fixture still in service.

Which record would you correct? In this fictional example, the first two statements could be true for cell A. The error was dropping the cell identifier when someone summarised the change. Copying the same status into three systems would make the records agree and leave the second cell exposed.

Give each record a decision to own. Carry the process, characteristic, scope and evidence reference across each handoff. Then a reviewer can see why a corrective action is closed for one cell while a wider risk still needs an owner.

Follow the locating pin

Cells A and B machine the mounting face of a housing. At operation 20, two locating pins with different shoulder heights can fit the same fixture. A short pin can leave the housing seated at the wrong height. In the example, a first-piece inspection on cell A catches a mounting face outside its height tolerance. The finding establishes what happened on A. It also gives the team a reason to check B.

Record and ownerDecision it ownsWhat belongs in the entry
Risk R-014 · operations managerWhich cells need attention, and who will review the remaining exposure?Both cells, mounting-face height, current controls and a dated decision for each cell.
PFMEA scenario F-020-07 · process engineerHow could this operation fail, with what effect, and what prevents or detects it?Wrong pin selection, incorrect seating, downstream fit effect, fixture design and first-piece check by cell.
CAPA C-031 · quality leadWhat happened on A, why did it happen, and what evidence supports closure for A?Affected lot, containment, tested cause, change scope, verification and effectiveness evidence.

These identifiers are an example convention. Keep the ID when a title changes. Give a PFMEA scenario a stable key even if the worksheet row moves. Keep the revision as a separate field so a reviewer can find both the analysis used for the original decision and its current version.

Start the register entry

In the free Qhubio builder, title the assessment Housing cell changeovers. Give the risk a concrete description: “An interchangeable locating pin can seat the housing at the wrong height at operation 20 in cells A and B.” Enter the operations manager as owner. Under existing controls, identify the shared storage tray and the first-piece height check. The tray is a selection condition; the inspection is a detection control. Write them so the reader can tell the difference.

To reproduce the example, select initial likelihood 3 and impact 4. The builder gives 12, High using its generic five-by-five matrix. The two inputs are illustrative judgements. For a live entry, use your organisation’s criteria, the history of comparable changeovers and the consequence of a missed check. Leave residual ratings pending until the owner has evidence for the stated scope. The calculator and PDF export are free. Saving and reopening the assessment requires an account.

A tool for the work
Build the entry for both cells, record the current controls, and put a named review of cell B in the mitigation field. Export the initial assessment so the team can reconstruct its starting point.
Start a risk register

The score belongs to that register entry. In the PFMEA, the team rates severity, occurrence and detection against the actual effect, cause and current controls under its applicable criteria. Register score 12 leaves detection unspecified and cannot determine Action Priority. Once the team has justified all three ratings for one scenario, it can check the combination in the FMEA Action Priority Calculator. Keep the technical analysis and rationale in the full Process FMEA.

Give each handoff a direction

Evidence handoffs · Operation 20One fixture change, three records
  1. Risk register to PFMEAAssess pin selectionBoth cells · operation 20
  2. PFMEA to CAPAInvestigate the failureCell A · first-piece inspection
  3. CAPA to PFMEAVerify the keyed fixtureCell A · acceptance test
  4. PFMEA to Risk registerReview remaining exposureCell B · previous fixture
Cell A Keyed fixture verifiedCell B Fit check still open

A useful link says what the recipient is being asked to do. “See CAPA” leaves that question open. A better note on F-020-07 reads: “C-031 tested pin selection on cell A. Review the prevention control for A against the fixture acceptance record. B uses the previous fixture.” A return link in the case points to the reviewed PFMEA revision. The records can live in separate tools.

Use the editable record-link worksheet to try this with your team. It has one row per handoff, including the sending and receiving IDs, cell, characteristic, evidence reference, receiving owner and review decision. Replace the example identifiers with stable links your reviewers have permission to open. A link to the current folder alone will lose the version behind a decision.

Reconcile the contradiction before closure

Imagine that the register now reads “keyed fixture installed on both cells.” The fixture acceptance record identifies A only. The PFMEA revision covers A only. The case owner has verified on A that the wrong pin cannot seat in the modified fixture. The quality lead can show first-piece results for subsequent changeovers on A. What is missing is evidence about B.

  1. Restore the boundary. The risk owner corrects the register to show the change on A and the existing arrangement on B. Keep the previous entry, change date and reason in the history.
  2. Check what was promised. Read the approved CAPA scope. If C-031 promised a two-cell rollout, it remains open or needs a formally reviewed scope change under the organisation’s process. If it covered A and its effectiveness criterion has been met, record that bounded closure and assign B a separate review.
  3. Verify the receiving record. The process engineer identifies which fixture revision the PFMEA describes. A planned change on B stays recorded as planned. Reassess affected ratings only when there is supporting evidence. A keyed fixture on A need not change the consequence of an out-of-tolerance housing.
  4. Name the next decision. The B supervisor checks which pins can physically be fitted and reviews changeover records before the next affected run. The operations manager owns the decision to extend, replace or retain the control and records the evidence used.

List the changes that trigger a cross-check: a fixture revision, a new affected cell, a customer escape, a failed effectiveness check or a changed acceptance criterion. The person making the change identifies the affected links. Each receiving owner records a decision, including a reason when their record needs no amendment. One risk can link to several PFMEA scenarios. A case can address more than one scenario. Keep a separate link for each relationship so closing one case cannot silently close them all.

At the next review, pick one recent change and follow it both ways. From the risk register, find the current control and its evidence. From the closed case, find the register owner who accepted the remaining exposure. If either direction stops at a copied colour, an inaccessible attachment or a superseded worksheet row, repair that link while the decision is still fresh.

Qhubio’s CAPA product is planned for launch. This convention can be used today with a register, a controlled PFMEA and the team’s existing case system. For the separate decision about opening a case, see when a quality event needs CAPA.

Review checklist

  • Each record has a stable ID, scope and accountable owner.
  • The operation, characteristic and affected cell match across each link.
  • A reviewer can open the evidence at the revision used for the decision.
  • A register score and a PFMEA Action Priority each have their own basis.
  • Every affected owner has accepted the change or recorded an open decision.

Sources and editorial basis

ISO’s overview of risk management explains why assessment, treatment and review depend on organisational context. AIAG describes the technical analysis and Action Priority method used in the AIAG and VDA FMEA approach. The identifiers, cell example, worksheet and handoff rules here are an editorial working method. ISO 31000 overview · AIAG on the FMEA Handbook

End of article